- How many square feet do we want/need?Prior to buildWeek 3 - 51
- Should the master bedroom face east or west?Prior to buildWeek 3 - 52
- Do we want all bedrooms on the second floor?Prior to buildWeek 3 - 53
- Footings formed and foundation pouredFoundation0 / 3Week 5 - 114
- Floor area fitted with utilitiesFoundation0 / 2Week 5 - 115
- Inspection 1FoundationWeek 5 - 116
- Shell/Skeleton completed (Floor system, walls and roof system)Framing PhaseWeek 5 - 117
- Plywood or oriented strand board (OSB) sheating appliedFraming Phase8
- Sheathing covered with cover/house wrapFraming Phase9
- Pipes and wiresRough Plumbing and Electrical10
- Water supply linesRough Plumbing and Electrical11
- Shower units and BathtubsRough Plumbing and Electrical12
- Sewer lines and ventsRough Plumbing and Electrical13
- Duckwork for HVAC* systemRough Plumbing and ElectricalWeek 12 - 1514
- HVAC* vent pipes installedRough Plumbing and ElectricalWeek 12 - 1515
- Electrician installs receptaclesRough Plumbing and Electrical0 / 3Week 12 - 1516
- Wiring for cable TV / music systems / telephonesRough Plumbing and ElectricalWeek 12 - 1517
- Inspection #2Rough Plumbing and Electrical18
- Insulation thermal performance/R-value test for heat transferInstall Insulation0 / 4Week 15 - 1719
- Kraft paper or foil-kraft paper attachment to vapor barrierInstall InsulationWeek 15 - 1720
- Drywall hung and tapedComplete drywall / interior texturesWeek 15 - 1721
- Drywall texturing (if applicable) is completedComplete drywall / interior texturesWeek 15 - 1722
- Primer coat of paint applied after taping completeComplete drywall / interior texturesWeek 15 - 1723
- Installing exterior finishesComplete drywall / interior textures0 / 4Week 15 - 1724
- Install exterior drivewaysFinish Interior trim25
- Install exterior walkwaysFinish Interior trim26
- Install interior doorFinish Interior trimWeek 15 - 1727
- Install doorsFinish Interior trimWeek 15 - 1728
- Install baseboardsFinish Interior trimWeek 15 - 1729
- Install door castingsFinish Interior trimWeek 15 - 1730
- Install window sillsFinish Interior trimWeek 15 - 1731
- Install moldingsFinish Interior trimWeek 15 - 1732
- Install stair balustersFinish Interior trimWeek 15 - 1733
- How many square feet do we want/need?1
- Should the master bedroom face east or west?2
- Do we want all bedrooms on the second floor?3
- Footings formed and foundation poured4
- Floor area fitted with utilities5
- Inspection 16
- Shell/Skeleton completed (Floor system, walls and roof system)7
- Plywood or oriented strand board (OSB) sheating applied8
- Sheathing covered with cover/house wrap9
- Pipes and wires10
- Water supply lines11
- Shower units and Bathtubs12
- Sewer lines and vents13
- Duckwork for HVAC* system14
- HVAC* vent pipes installed15
- Electrician installs receptacles16
- Wiring for cable TV / music systems / telephones17
- Inspection #218
- Insulation thermal performance/R-value test for heat transfer19
- Kraft paper or foil-kraft paper attachment to vapor barrier20
- Drywall hung and taped21
- Drywall texturing (if applicable) is completed22
- Primer coat of paint applied after taping complete23
- Installing exterior finishes24
- Install exterior driveways25
- Install exterior walkways26
- Install interior door27
- Install doors28
- Install baseboards29
- Install door castings30
- Install window sills31